Aug 22,
2012 (LBO) - Sri Lanka's Chinese built coal plant which is breaking down
repeatedly has been over-used without scheduled maintenance but had still saved
billions of rupees to the power utility, its designer has said.
Zhao Wenxue, from the Northwest Electric Design
Institute which designed the plant said in a statement that most of the
accusations leveled against the plant, built by China Machinery Engineering
Corporation (CMEC) are unfair.
The plant had been well designed but had been operated
from March 2011 without annual maintenance he pointed out.
"According to normal practice in China, a thermal
plant should undergo a one month maintenance period annually," Wenzue was
quoted as saying in a statement.
"Only then can the unit be more reliable and
efficient and expected to perform well.
"The lack of rain at the hydro catchment areas in
Sri Lanka over the past several months posed a threat to the power generation
around the island.
"The Norochcholai coal power plant was forced to
work beyond its required limits and keep supplying electricity to the whole
country.
"With the lack of rain and in an attempt to avoid
burdening the public with power cuts the Ceylon Electricity Board had meanwhile
decided to postpone the annual maintenance of the Norochcholai coal power plant."
Another source familiar with the matter said the plant
is still within a 'defect notification period' which usually follow a large
engineering project before being finally handed over to the client.
A coal plant cannot be compared to a hydro or diesel
plant as it is more complex and problems also crop up when a plant is shut down
and re-started. Some problems have to be repaired while the plant is still in
operation Wenzue said.
Some of the technical aspects of such a plant also
need to be maintained and repaired while the plant is in operation.
Wenzue said CEB and CMEC engineers were working around
the clock to fix the problems.
"The Norochcholai coal power plant had past all
the performance tests and it was in operation continuously from February 2012
till end of July 2012," he said.
"Questioning the quality of the equipment used in
the project and pointing fingers at CMEC is without basis.
"The Norochcholai coal power plant is not as bad
as one makes it look. It is just overused, tired and needs a break to rest like
any other equipment does."
Analysts says that a coal plant would in any case be
expected to about 80 percent of the time (plant factor) which would allow the
300MW plant to generate about 2,100 GigWatt hours of energy a year.
During the past year the plant had generated 1,875
GigaWatt hours (millions of units of electricity) at a cost of 6.67 rupees a
unit at a total cost of 12.5 billion rupees.
To generate the same amount from a combined cycle
plant at 15.79 rupees a unit would cost 29.6 billion rupees.
Assuming 80 percent of that energy came from a
combined cycle and 20 percent from gas turbines (at 25.93 rupees a unit) it would
have cost the CEB 33.4 billion rupees to generate the same amount of energy,
Wenzue said.
Following the ground breaking ceremony in July 2007,
on a request by Sri Lanka, the Chinese government had asked the builders to
complete the project one year ahead of schedule.
"We agreed and mobilized our teams including a
skilled workforce for early completion of the project ahead of the scheduled
date," Wenzue said.
The design build transfer project was financed with a
Chinese loan. The coal plant was long overdue.
However concerns have been raised about the way the
deal was closed between the ruling classes of Sri Lanka and China through a
so-called 'government to government deal' without open tendering.